The first stage of the building construction which is preparation of foundation trenches setting up of foundation bases and walls have been a success story. Currently the construction team is in the final stage of the first stage (construction of the sub structure) which is 80% to completion.

Note: The bases of the sub structure was designed in such a way that it will withstand vibrations ,internal and external pressures as a formidable hardcore combined with well compacted laterite fillings formed part of its mass concrete floor.

Attached are pictorial illustrations on work progress on site.