The Job center construction kicked off on the 8th of January 2018 with excavations. Almost all the wall partitions formed part of the sub structure.

Reason: They are load bearing walls,hence must come up from earth so as to transfer loads directly to the ground which is the ultimate load bearer.

* A blinding thickness of 4" inches was layer on the foundation trenches. 9" inches block served as walls sub structure preparation and will also be used in super structure (surface) construction

* The building witnessed an introduction of columns at the discretion of the site project manager/Trainer .This is to ensure stability and check on future cracking of the building since it spans beyond 30 metres .hence a structural columns at 5 metre interval .

* Height of DPC also was elevated to standard.

Our trainees paying attention to details to the trainer / site Project manager .